Approximate bill of quantities vs approximate quantities cost plan
An approximate bill of quantities should not be confused with an approximate quantities cost plan. This article explains the differences between them.
An approximate bill of quantities can be used on projects where it is not possible to prepare a firm bill of quantities at the time of tendering. Generally, the design will be relatively complete, but there is either insufficient time or information to determine the exact quantities required and so a conventional bill of quantities cannot be prepared.
For more information, see Approximate bill of quantities.
An approximate quantities cost plan is part of the iterative cost planning process and is a development of the elemental cost plan. Unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects), the approximate quantities cost plan is a first attempt to measure defined quantities from drawings. In effect, it is a costed approximate bill of quantities.
For more information, see Approximate quantities cost plan.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.